Operational acceptance and go-live readiness

  • Lesson 4 of 5
  • Architect
On This Lesson 4 topics

This lesson is planned. The outline below lists the topics it will cover. The full lesson has not been published yet.

In this lesson

verify the solution can be run, and decide go-live readiness from evidence.

Planned topics

  • Operational acceptance checks monitoring, alerting, runbooks, backup and restore, support rota, access, and escalation paths with vendors.
  • Verify by doing: restore a backup, trigger an alert, run an incident drill, not by reading a checklist.
  • Readiness combines functional results, NFR evidence, operational acceptance, migration and rollback readiness, and open risks.
  • Recommend go, conditional go (with named conditions and dates), or no-go; trace each to evidence.
  • The business accepts residual risk explicitly; the architect does not hide it.
Draft outline details

Demonstration

a go-live readiness table: criterion, evidence, status (met, partly, not met), residual risk, owner; with a final recommendation line.

Check your understanding

What is a conditional go?

Show answer

Go-live approved only if named conditions are met by given dates, with an accountable owner.

Practice

Apply this lesson with the module's lab, exercises and quiz.

Lab and exercises Quiz