Demo: a pilot-store rollout and its rollback plan
On This Lesson 3 topics
This lesson is planned. The outline below lists the topics it will cover. The full lesson has not been published yet.
In this lesson
worked rollout for pilot stores with a defined rollback; prepares ARC-037-LAB1.
Draft outline details
Step by step
- Choose three pilot stores: different sizes and connectivity; stakeholders agree the success measures.
- Define go/no-go criteria: till tests passed, staff trained, support on site, data validated.
- Run the cutover for the stores with the runbook; monitor sales, errors, and queue times.
- Planned mistake: a rollback plan that restores the old till configuration but ignores sales recorded on the new system. Fix: define how new-system sales are exported and replayed, with an owner.
- Review after two weeks; decide the next wave using the exit criteria.