Planned lessonARC-037-L06

Demo: a pilot-store rollout and its rollback plan

  • Lesson 6 of 6
  • Architect
On This Lesson 3 topics

This lesson is planned. The outline below lists the topics it will cover. The full lesson has not been published yet.

In this lesson

worked rollout for pilot stores with a defined rollback; prepares ARC-037-LAB1.

Draft outline details

Step by step

  1. Choose three pilot stores: different sizes and connectivity; stakeholders agree the success measures.
  2. Define go/no-go criteria: till tests passed, staff trained, support on site, data validated.
  3. Run the cutover for the stores with the runbook; monitor sales, errors, and queue times.
  4. Planned mistake: a rollback plan that restores the old till configuration but ignores sales recorded on the new system. Fix: define how new-system sales are exported and replayed, with an owner.
  5. Review after two weeks; decide the next wave using the exit criteria.

Practice

Apply this lesson with the module's lab, exercises and quiz.

Lab and exercises Quiz

Marking a lesson complete is optional and you can undo it any time. Your progress stays in this browser.

Type to search levels, phases, modules and lessons.