Buying information early
On This Lesson 4 topics
This lesson is planned. The outline below lists the topics it will cover. The full lesson has not been published yet.
In this lesson
reduce uncertainty early at low cost.
Planned topics
- Spike: time-boxed investigation to answer a technical question.
- Prototype: a thin end-to-end slice that exposes integration problems.
- Staged commitments: commit to the next stage, not the whole program, until risks fall.
- Tackle the riskiest, least understood parts first, not the easiest.
- Record what you learned and update the register.
Draft outline details
Demonstration
A table: risk | question | spike or prototype | time box | decision it enables. Example: can we sync stock at the required rate? | load spike on sync path | 3 days | choose events or batch.
Check your understanding
Why do risky work first?
Show answer
Learning early leaves time to change the plan.
Practice
Apply this lesson with the module's lab, exercises and quiz.